Duan Mei
-
Appearance completed -
Completion of exterior wall demolition and construction of landscape paving works -
Exterior wall decoration construction -
Completion of structure and exterior wall decoration construction -
The 4th floor structure of Area A and Area B is completed. -
Construction of 4FL in Area A and 2FL in Area B -
Construction of 1FL in Area A and B1FL in Area B -
B1FL structure construction -
Earth excavation and internal support engineering construction -
CCP pile construction -
Pre-pile construction -
land preparation